SV Pilgrim - 1979 Morgan 382 - Homeport: Beaufort, NC

Sunday, September 6, 2015

Replacing the Leaking Quarterberth Port, the Exterior Story – Part 1

Our previous post, Replacing the Leaking Quarterberth Port, the Interior Story, explains why, and how we removed the original port.  The post also shares our reasoning for replacing the port with fixed pane window.

As many boat projects are apt to do, the exterior story begins with… creating a template. 

Creating a 1/4" plywood template of the window pane.
Yes, that is an electrical tape canister we are using for the corner radius. 

The template will allow us to “test” the aesthetics of the panel prior to cutting into our limited supply of acrylic material.  The template will also serve as a guide for the router bit used to trim the acrylic.  ½” plywood was my preferred template material.  Unable to find an appropriate piece of scrap we used ¼” plywood.

Pleased with the look and fit of the template, we then transferred the shape to the masked acrylic.

Template dimensions transferred to the masked acrylic sheet.

Ok, time for a disclaimer… our experience working with acrylic, Lexan, Plexiglass, and similar materials is very limited.  We welcome any comments or suggestion on working with these types of materials. 

The material we are using is ½” thick Chemcast Cell Cast Acrylic Sheet.  We reclaimed the scrap material from a project on another vessel.  Since the material was previously installed it lacked the protective coating found on virgin material.  When possible we kept the pane masked with painters tape during the install process.

Prior to cutting the actual pane, I experimented with various cutting tools and techniques.  The jigsaw with Plexiglas specific blades generated too much heat.  The heat melted the acrylic and created a rough, scored edge.  Perhaps the jigsaw blades would work better on thinner material?  Using the hand held circular saw with a multi-purpose blades (24 to 40 teeth) yielded similar results to the jigsaw.   The best solution I found was to use a fine crosscut blade (90 teeth) in the circular saw to rough cut the acrylic. Then use a router with a flush trim bit for the final shaping.

With the template as a guide, I used a router with a flush trim bit to clean up the edges of the acrylic window pane.

I clamped the rough cut pane atop the plywood template.  The template then served as a guide for the flush trim router bit.  Since the guide wheel on the router bit transfers any irregularities from the template to the finish material it is important to sand down the rough edges of the template.  Yeah, I learned this the hard way.

Unfortunately the painters tape masking did not play nice with the router.  My solution…

Masking the base of the router proved more effective than masking the acrylic face.

Remove the masking from the acrylic and place a couple strips of masking on the base of the router.  Masking the base of the router worked for both the flush trim bit and the round over bit used to radius the outside edge of the pane. 

Next the edges of the acrylic were sanded beginning with 220 grit and progressing up to 600 grit sandpaper.  Sanding the edges up to 600 grit brought them back to a dull, smooth surface.  I certain by a polished edge could be achieved if so desired.


To Be Continued…

Friday, September 4, 2015

Replacing the Leaking Quarterberth Port, the Interior Story.

While sanding in the engine compartment, a passing a rain shower alerted me to how badly the old, plastic quarterberth port was leaking.  All the other ports in the Pilgrim are New Found Metal Stainless Steel ports, installed by a previous owner.  Replacing the only remaining original plastic port was on the project list.  Watching row of steady drips along the starboard side wall of the engine compartment elevated the project priority.

We believe the plastic port in the quarterberth was installed at the factory in 1979.

Frequently after rains I check the quarterberth area for water intrusion.  Never found any signs the port was leaking.  It never occurred to me to check the engine compartment.  The leak originated around the outer flange of the port. The water then dripped down thru the void between the fiberglass wall of the cockpit foot well and the ¾” plywood cabinetry wall of the quaterberth.

The original port, set in copious amounts of silicone sealant, heartily resisted removal.  Ultimately the combination of a razor knife and pry bar won the day. 

The exterior view of the hole remaining after the port was removed.

After sanding down the surrounding surfaces, I filled the nearly 1-1/2” wide void around the perimeter of the opening with trimmed down pieces of a pressure treated 2” X 4”.

Fitting treated wood plugs into the void around the perimeter of the opening.

The wood plugs fit snuggly.  Once in place, I mechanically fastened the wood filler to both the outer fiberglass and the interior plywood using flat head stainless steel screws.

Filling gaps and irregularities around the opening with thickened epoxy.

Next, the remaining gaps and irregular surfaces were filled with cabosil thickened epoxy.  After sanding down the initial round of epoxy filler, the fairing began.

Round one of fairing viewed from the interior.

Fairing required two rounds of epoxy thickened with a micro-balloon filler (q-cells).  Each round of filler was followed by additional sanding.

Two rounds of fairing completed.  Now ready for primer.

The interior surfaces were finished with two coats of latex primer and two coats of exterior grade latex paint.

The interior completed.  Test fitting the masked acrylic window pane.

Since we intend to use Pilgrim’s quarterberth  as a storage area only, we chose to install an acrylic window pane rather than a new opening port.  We realize not installing an opening port will reduce ventilation in the area.  We have scrap pieces of tinted acrylic on hand.  New ports are very expensive.  Using the acrylic will save us money.  The window will provide natural lighting for the storage area.

View from the interior with the new window installed.

See our Quarterberth Refit Photo Album for images and notes current progress on this project.


Next up, the outside story… fabricating and installing the new acrylic window pane.

Sunday, August 23, 2015

New Companionway Drop Boards

Rare is the boat project that can be completed in a single afternoon. 

Pilgrim's tired, teak drop boards.
Pilgrim arrived in Beaufort with three teak companionway drop boards.  The existing teak drop boards are both too thin, between ½” and 5/8”, and too short.  Due to the inadequate size, the boards would bind up unless extreme caution was employed when removing or installing them.

The solution?  Two new ¾” thick King Starboard drop boards.  Since the Starboard does not require painting or varnishing, the project fit neatly into a couple hours…
  • Lay out the proper dimensions.
  • Rough cut the Starboard with a circular saw.
  • Using a router, create a rabbit joint between the upper and lower boards.  Set up the joint to shunt water outside the boat.
  • Using flush trim and round over bits in the router, finish the edges of the boards.
  • Install the hasp.


Pilgrim's new Starboard drop boards.

The new boards slide easily in and out of position.  Unlike the top of the slider or the exterior companionway step pictured above, the new drop boards will never require refinishing. 

We plan to replace all the exterior teak in the image above… in due time.


Sunday, August 16, 2015

Painting Ice Box and Engine Beds

We chose to use Alexseal Epoxy Primer and Alexseal Premium Topcoat for the engine compartment beds and surrounding  hull.  Why the Alexseal? 
  • We used the same system on the interior of the new ice box and are very pleased with the finished product. 
  • The Alexseal system will create a durable, glossy, easily cleaned surface. These attributes are desirable in both the engine compartment and the ice box.
  • We need to paint the seam along the aft wall of the ice box. Using the same paint will allow us to tackle both the engine compartment and the ice box project at the same time.

I know it’s been awhile since we mentioned the ice box rebuild (Ice Box Rebuild Photo Album).   We completed the fabrication of the new ice box last spring.  Painting the seam along the aft interior wall remained unfinished.

Seam along the aft wall of the ice box is prepped and ready for primer.

Building up the Alexseal epoxy primer "wet on wet" creates a stronger bond between the layers and eliminates sanding between coats.  How to reach the aft end of the compartment without marring the still tacky primer? 

The lower engine compartment ready for primer.

I experimented with painting the aft area via the cockpit locker and quarterberth access panels, but this proved too awkward.  My solution... leave the tops of the engine beds for another round of painting and place a piece of ¾” plywood across the beds.  This created a stable, albeit slightly angled, platform above the curing primer.

3/4" Plywood painting platform atop the engine beds.

Using this system I applied four coats of primer…

Four coats of epoxy primer complete.

The primer must cure for a minimum of 3 hours between coats.  The four coats of primer when on over a two day time span. The primer must be allowed to cure for 24 hours and then sanded before the top coat application. 
   
When using a brush to apply top coats a 24 hour cure time followed by sanding is required between coats.  The sanding generates unwanted dust so the area must be cleaned and wiped down in prep for the next coat.  Applying the two top coats occurred over a four day time span.

The finished product... a blank canvas on which to begin the engine install.

The top of the engine beds still require some primer and paint.

The top of the engine beds will be painted along with the interior face of the ice box lid.  The ice box lid is still under construction, but the ice box interior is looking good.

The interior of the new ice box is ready for divider & shelving installation.


The next step on the ice box is to install the vertical divider and the shelves.

Saturday, August 8, 2015

Painting Engine Beds and Surrounding Hull - Part 1

Somewhere in Pilgrim’s past a previous owner did a poor job of applying oil based paint to the engine beds and a portion of the surrounding hull.  Removing the paint with a heat gun and paint scraper would be the best case scenario.  Since we are discussing good old boat project the best case scenario failed.  



Masking the engine compartment in prep for grinding after failing to remove the paint with heat ans a scraper.

The two somewhat bare areas between the beds in the image above mark my attempts to heat and scrape. The effort resulted in gouges; strands of woven-roven mat tearing away from the hull; and paint left in the low spots. 

What next? 

Mask every opening, see images above and below.

draping plastic sheeting across the engine compartment access in an effort to contain the dust.

Suit up.
 
Plug in the grinder and shop vac.

Crawl under the plastic and into the engine compartment with the power tools.   

Generate vast amounts of dust while sweating out gallons of fluid.

On round one I succumb to the heat after sanding the aft half of the area.

The aft portion of the engine compartment hull completed in round one.

For round two, the next day, I rigged a box fan to pull air and dust out via the locker under the helm seat.  By the end of round two all the grinder accessible areas were completed. Everything the grinder was unable to reach… outboard of the beds and the narrow area along the centerline… required hand sanding.

Round three, four, five... multiple 60 to 90 minute sessions of hand sanding with 40 grit paper stretched out over a couple days.  The initial session taught me to wear leather gloves when driving 40 grit sandpaper.   

Majority of sanding completed.

The grinding and sanding revealed a couple areas requiring some minor fiberglass repair.

De-laminated area along forward, starboard bed removed.
Crack in fiberglass mat along forward, port engine bed.
I was able to repair these issues in a single session of epoxy work

Few layers of 1708 cloth covered with a single layer of finish cloth.

While working the area, I noticed the irregular texture and pitch of the center line caused water to pool in a few areas.  No time like the present to address this issue.

Fairing the center line to allow for proper water drainage.

Using tropical hardener to allow for a thick lay up in the summer heat, I mixed up a batch of epoxy thickened to a honey consistency.   This mixture was poured into the center seam near the stern.  With only some minor coaxing from a spreader, I allowed the thick fluid to find its own level.  Once the epoxy began to kick, I laid a single layer of finish cloth across the top.

Once all the repair work was completed the area receive a thorough cleaning with Tri-Sodium Phosphate (TSP).

Engine beds and surrounding hull ready for the first coat of primer.

The area is now masked and ready for primer.

See our Repowering Photo Album for images and notes current progress.


Monday, August 3, 2015

Refinishing the Engine Compartment Overhead & Walls

The best illustration I could find of the existing paint in the engine compartment is a dated image (old drain manifold, hole from original engine raw water intake on port, refrigeration lines feed into ice box, and no bulkhead separating the engine compartment from the cockpit locker).

Old image of Pilgrim's engine compartment that illustrates the need for repainting the area.

The image does do a good job of illustrating the dingy, tired paint on the walls; a lack of paint overhead, and the poor quality oil based paint applied to only a portion of the hull. 

We decided to take a top down approach to painting the engine compartment.  We began with the overhead and vertical side walls.  Most of the surfaces required only minor prep work… TSP wash down followed by two rinses with fresh water.  The overhead was previously lined with decaying soundproofing material.  The sound proofing was easily removed. The steel sound proofing mounting tabs were epoxied to the overhead.  The epoxied tabs quickly succumb to a hammer and old chisel.   The forward, interior of the cockpit foot well (see brown area in image below) was also covered with sound proofing material.  Unlike the overhead this section of sound proofing was glued to the boat.  The heavy application of contact cement proved very stubborn.

State of Pilgrim's engine compartment prior painting.

Rather than engaging in a prolonged battle to excise the old glue, we fabricated a plywood panel for the area.  Once again we reused sections of the original salon aluminum angle for mounting the plywood panel.  The plywood has the added benefit of allowing us to easily mount wiring, electrical components, hoses, etc.

Overhead and side walls of engine compartment painted.

We plan to install new sound proofing material on the two port access panels, the starboard access panel, the forward access panel, and the overhead.  The sound proofing will be added once all the other dust producing projects are completed.


See our Repowering Photo Album for images and notes current progress.

Saturday, August 1, 2015

Back to Producing Dust

Our recent progress with installing electrical and plumbing components really inspires me to continue work on those systems, but some items remaining on our project list require grinding inside the hull.  Grinding inside generates awful gelcoat and fiberglass dust.  Despite our best efforts at masking the fine dust always finds its way into the rest of the boat.   Thus, we really need to complete all the projects that require grinding inside the hull, prior to installing additional electrical, plumbing, or mechanical parts.

What is on the get the grinding done list?
  • Repair some detached fiberglass mat on the engine beds.
  • Paint the engine compartment and beds.
  • Relocate engine exhaust thru-hull.
  • Tabbing modifications and repairs to area around steering quadrant.
  • Install mounting platform for new, below decks autopilot.
  • Paint locker under helm seat.

We plan to start with the painting the engine compartment.

Thus far in our refit we have used the forward cabin for storage of cushions.  Other than removing a depth transducer we have completed no interior work in the forward cabin or anchor locker.  There are dust generating, messy projects forward (anchor locker modifications, tabbing between bulkheads and deck, etc.).  Since this area is relatively easy to seal off from the aft portion of the interior, we plan to address this area at a later date.

With respirator and grinder in hand, I’m off to generate some dust.


Friday, July 31, 2015

Nav Station Instruments and Electrical Panel Façade – Part 2

Installing panels in the frame required creative hinge work.

Test fitting new nav station electrical and instrument panels.

To provide the most ergonomic access to the backside of the panel we chose to hinge the aft, electrical panel section along the forward, vertical side.  Hinging the panel to swing forward provides easy access to the panel while sitting at the nav station.   It also places additional stress on the hinge.  To accommodate the additional forces I chose to surface mount the hinge. Then thru-bolted machine screws to attach the hinge to the panel. 

The BassPanel contains 20 D/C breakers, 8 A/C breakers, an A/C reverse polarity indicator, analogue load gauges for both D/C & A/C systems, and analogue voltage gauges for both D/C & A/C systems.

Being uncertain what devices may be added to the forward panel in the future, I felt the best option was to place the hinge along the lower, horizontal edge of the panel.    Thus panel swings down and rests atop the nav station desk.  This action provides access to the back side of the panel while sitting at the nav station.  Accessing the items mounted on the hull outboard of the panel can be achieved by kneeling on the nav station bench seat.

The forward, instrument panel hinges down.  The aft, electrical panel hinges forward.

I recessed the foreword panel slightly by installing the hinge to the vertical face of the panel and the horizontal edge of the frame.  This provides additional clearance between devices installed in the panel and the hinged nav station desk top that swings upward when opened.

The final install will include trim along the top and an arm rest / storage below the aft section.

Currently panel is simply slid into place for test fitting.  For the final installation we will secure it with screws and add trim along the top edge.  We also plan to build an arm rest / storage below the electrical (aft) panel.  The arm rest will hide the wire runs entering the panel from below.


See our Navigation Station Re-Fit Photo Album for images and notes current progress.